The Capital Development Authority (CDA) has accelerated construction work on the Margalla Avenue extension connecting N-5 to M-1, along with the Sangjani Interchange. According to the authority, approximately 43% of the overall project has been completed, with construction teams working around the clock on the chairman’s instructions.
The project includes an approximately 2.7-kilometre extension of the main roadway within Islamabad Capital Territory. Work is progressing across multiple sections, with all loops and ramps nearing completion. Construction of the service road connecting to the main carriageway is also underway.

Underpass and Sangjani Interchange Progress
The CDA has completed the underpass structure, including its concrete walls and footing slabs. At Sangjani Interchange, piling and girder installation have also been completed.
Steel reinforcement work is currently in progress, while excavation work is expected to be completed soon.
Progress on N-5 Bridge and Culverts
Construction teams have completed piling and excavation for the abutments on both sides of the N-5 bridge. Four culverts have also been completed, while work on the fifth culvert continues.

CDA Chairman Directs Teams to Maintain Construction Quality
CDA Chairman Sohail Ashraf has instructed the project teams to complete construction while maintaining quality standards.
He said the Margalla Avenue extension would provide an important entry route into Islamabad for people travelling from other cities, particularly those coming from Khyber Pakhtunkhwa.
Ashraf also highlighted the project’s importance for improving access to Islamabad International Airport, making journeys more convenient for commuters travelling to and from the capital.